PROJECT DESCRIPTION
The purpose of this project was to replace Hydro One’s existing 12 x 115 kV underground low pressure liquid filled cables (H2JK ca1 & ca2 and K6J ca1 & ca2) that were installed in 1957, which are now at or nearing end of life from Riverside Junction to Strachan TS.
B&M SCOPE OF WORK
The work required was engineering, procurement and construction of two new 230 kV circuits to be installed in a concrete duct bank in place of one of the existing direct buried cable circuits. The installation was a combination of open cut and directional drilling and/or tunneling within the existing right of way boundaries, installation of 14 chambers, and installation of 36 km of 4,000 kcm 230 kV cable. Removal of existing 115 kV cable and oil accessories was also required.
The scope included:
- Design, supply and installation of 230kV XPLE cable – 5.6 km underground
- Design, supply and installation of directional drilling (and/or tunneling) and open cut along the existing cable route – approximately 5.6 km
- Laying approximately 6 x 5.6 km of 230 kV XPLE single core XLPE cables
- Cable splicing and termination materials
- Installation of all splicing and cable terminations in Riverside Junction and Strachan TS
- Dress cables and final termination
- Cable testing AC High Pot, PD testing and DTS modelling.
- Cable pulling / transportation
- Back filling
- Handling, storage, transport, testing and disposal of all excavated materials
- Handling, storage, transport, testing and disposal of all oil in the decommissioned cables
Related Project Profiles

Yonge Street Rapidway
Black & McDonald was tasked with widening Yonge Street in the cities of Richmond Hill and Newmarket for dedicated Viva bus lanes.

Toronto Hydro Electric System Substation
Black & McDonald performed inspections and testing on several aspects of the site, including protection and control systems, and switchgear and circuit breakers.

Armow Wind Farm Testing
Black & McDonald’s Field Service Division was contracted to perform a wide range of work, including point-to-point verification of all control and secondary…

Halifax Airport Installation
When the Halifax International Airport Authority needed to install new equipment vital to powering the operation of the airport, Black & McDonald applied…

Bruce Power Nuclear Generating Station
Black & McDonald was responsible for the complete re-commissioning of the relay protection for the MOT transformer, UST transformer, bus, line differential, breaker…

Cypress Substation Construction
Black & McDonald was contracted to construct a new 138 kV to 240 kV substation (109 m x 198 m).

407 ETR Phase 1 East Extension
Black & McDonald was the integrated electrical and civil contractor on this Design, Build, Finance and Maintain (DBFM) contract involving a 31 km…

TransCanada Napanee Generating Plant
Black & McDonald was the electrical contractor responsible for electrical completion work on all balance of plant electrical power systems (126 systems) at…

Oshawa Indoor Station Construction
Black & McDonald supplied all labour, materials, supplies, equipment, services and incidentals necessary to design, construct and commission the project.

Newmarket Hydro Substation Operations
Black & McDonald performed detailed inspections and testing on protection and control systems, SCADA systems and power transformers.

City of Toronto Utility Relocation
Black & McDonald was chosen by the City of Toronto for a construction contract extending the Path system at Front and York Street.

VivaNext Electrical Works
Black & McDonald performed widening of a 4.2 km stretch of Highway 7 between Highway 400 and the GO Bradford/Barrie Railway line in…

Veridian Connections Substations
Black & McDonald performs high-voltage maintenance, oil analysis and infrared scanning at various districts and substations on a regular basis.

MTO Variable Message Sign Upgrade
Black & McDonald was contracted to complete the upgrade and extension of the Advanced Traffic Management System Variable Message Sign system on Highway…

Grand Bend Telecom Buildings
Black & McDonald was awarded a contract for the detailed engineering, procurement of materials, and construction of two protection, control and telecom buildings.

GDF Suez – Erieau Wind Farm
Black & McDonald’s Field Service Division was contracted to perform a wide range of services, including review of design drawings including single lines,…

Innpower Substations Operations
Black & McDonald was tasked with performing high-voltage maintenance, repairs, oil analysis and infrared scanning. Projects included design, procurement, installation setting development and…

Clarington Transformer Station –Clarington TS 500kV to 230kVStep Down Transformer Station
Black & McDonald performs high voltage maintenance at various different substations, substation construction, OH line and civil construction.

St. Isidore Transformer Station
Black & McDonald was awarded the complete design, procurement and construction/installation of the 230 kV / 44 kV DESN station.

Horizon Utilities Substation Operations
Black & McDonald performs high voltage maintenance at various different substations, substation construction, OH line and civil construction.

Grand Bend Wind Farm
Black & McDonald's Field Service Division was contracted to perform a range of services, including commission and test complete electrical system, and review…

Construction of Grand Bend Wind Farm
Together with Black & McDonald’s Joint Venture Partner AMEC, the Southern Ontario Utility Region was awarded the Engineering, Procurement and Construction (EPC) contract…

Alectra Electrical Rebuilds
Black & McDonald was trusted with a contract for underground electrical rebuilds for Alectra and Utilities in the Hamilton and St. Catharines area.

EnWin Service Agreement
Black & McDonald was responsible for the Tecumseh Road East feeder extension.

Enbridge Ontario Wind Farm
The AMEC Black & McDonald Joint Venture was contracted to build the following 110 concrete wind turbine foundations and erect 110 wind turbines.

Underwood & Cruickshank Wind Farms
Black & McDonald was contracted to perform a wide range of maintenance services.

MTO – ATMS for various highways
An ATMS needed to be upgraded and reconfigured after the Ministry of Transportation established a new traffic operation centre at 97 Arrow Road…

Enbridge – Talbot Wind Farm
Enbridge’s 99 megawatt Talbot Wind Project generates enough clean energy to power 33,000 homes and offset about 106,600 tonnes of carbon dioxide each…

Clarington Transformer Station
Black & McDonald was engaged to conduct pre-service testing and commissioning of an important transformer station.

Capstone Erie Shores Wind Farm
Black & McDonald’s Field Service Division was contracted to perform a wide range of services, including review design drawings such as single lines,…

Belle River Wind Farm
Black & McDonald was contracted to construct a new 138 kV to 240 kV substation (109 m x 198 m).

K2 Wind Farm
Together with Black & McDonald’s Joint Venture Partner AMEC, Black & McDonald’s Southern Ontario Utility Region was awarded the engineering, procurement and construction…

Minas Energy St. Croix Hydro Dam
Black & McDonald assisted Minas Power with grounding update of its hydro system.

Halifax Airport Taxiway Restoration
Black & McDonald supplied and installed inset lighting, including underground conduit with all associated trenching, backfilling and wiring.

K2 Wind Farm
Black & McDonald’s Southern Ontario Utility Region engineered, procured and constructed the K2 Wind Farm, including installation of 140 Siemens wind turbines.
Get In Touch