
Clarington Transformer Station –Clarington TS 500kV to 230kVStep Down Transformer Station
PROJECT DESCRIPTION
Black & McDonald (B&M) constructed a transformer station for Hydro One Networks Inc. called “Clarington TS”. The station is located in the municipality of Clarington, which is in the eastern part of the Greater Toronto Area (GTA).
The purpose of this project was to replace 3,000 megawatts of capacity that at the time was supplied by the largest nuclear generation station in the GTA (Pickering Nuclear Generation Station), which was slated for decommissioning. When Clarington TS was fully commissioned it would be able to offset the generation loss with transmission capability and supply as much as 25 per cent of the East GTA’s electricity demand.
B&M SCOPE OF WORK
Supply of Equipment, Materials and Labour for Construction, Testing and Commissioning of Clarington (500 kV to 230 kV) for the Step Down Transformer Station included:
- Nine km of station drainage
- Two 500 kV circuit breakers and sixteen 230 kV circuit breakers
- Two 230 kV bus tie breakers
- Two 750 MVA auto-transformers
- Two 230 kV capacitor banks and two 230 kV capacitor bank breakers
- Two 750 MVA station transformers
- One ATS building
- Two relay buildings
- Over 200 km of cable
- Over 1,300 structural steel members and foundations
- Over 148,000 sq. m. of yard stone material
- At the peak of the project’s construction there was close to 70 tradespeople and project staff onsite.
BENEFITS TO THE CLIENT
B&M supplied equipment, materials and labour for construction, testing and commissioning of the Clarington TS step down transformer station.
Related Project Profiles

Yonge Street Rapidway
Black & McDonald was tasked with widening Yonge Street in the cities of Richmond Hill and Newmarket for dedicated Viva bus lanes.

Toronto Hydro Electric System Substation
Black & McDonald performed inspections and testing on several aspects of the site, including protection and control systems, and switchgear and circuit breakers.

Armow Wind Farm Testing
Black & McDonald’s Field Service Division was contracted to perform a wide range of work, including point-to-point verification of all control and secondary…

Halifax Airport Installation
When the Halifax International Airport Authority needed to install new equipment vital to powering the operation of the airport, Black & McDonald applied…

Bruce Power Nuclear Generating Station
Black & McDonald was responsible for the complete re-commissioning of the relay protection for the MOT transformer, UST transformer, bus, line differential, breaker…

Cypress Substation Construction
Black & McDonald was contracted to construct a new 138 kV to 240 kV substation (109 m x 198 m).

407 ETR Phase 1 East Extension
Black & McDonald was the integrated electrical and civil contractor on this Design, Build, Finance and Maintain (DBFM) contract involving a 31 km…

TransCanada Napanee Generating Plant
Black & McDonald was the electrical contractor responsible for electrical completion work on all balance of plant electrical power systems (126 systems) at…

Oshawa Indoor Station Construction
Black & McDonald supplied all labour, materials, supplies, equipment, services and incidentals necessary to design, construct and commission the project.

Newmarket Hydro Substation Operations
Black & McDonald performed detailed inspections and testing on protection and control systems, SCADA systems and power transformers.

City of Toronto Utility Relocation
Black & McDonald was chosen by the City of Toronto for a construction contract extending the Path system at Front and York Street.

VivaNext Electrical Works
Black & McDonald performed widening of a 4.2 km stretch of Highway 7 between Highway 400 and the GO Bradford/Barrie Railway line in…

Veridian Connections Substations
Black & McDonald performs high-voltage maintenance, oil analysis and infrared scanning at various districts and substations on a regular basis.

MTO Variable Message Sign Upgrade
Black & McDonald was contracted to complete the upgrade and extension of the Advanced Traffic Management System Variable Message Sign system on Highway…

Grand Bend Telecom Buildings
Black & McDonald was awarded a contract for the detailed engineering, procurement of materials, and construction of two protection, control and telecom buildings.

GDF Suez – Erieau Wind Farm
Black & McDonald’s Field Service Division was contracted to perform a wide range of services, including review of design drawings including single lines,…

Innpower Substations Operations
Black & McDonald was tasked with performing high-voltage maintenance, repairs, oil analysis and infrared scanning. Projects included design, procurement, installation setting development and…

Hydro One Underground Circuits
The work required engineering, procurement and construction of two new 230 kV circuits to be installed in a concrete duct bank in place…

St. Isidore Transformer Station
Black & McDonald was awarded the complete design, procurement and construction/installation of the 230 kV / 44 kV DESN station.

Horizon Utilities Substation Operations
Black & McDonald performs high voltage maintenance at various different substations, substation construction, OH line and civil construction.

Grand Bend Wind Farm
Black & McDonald's Field Service Division was contracted to perform a range of services, including commission and test complete electrical system, and review…

Construction of Grand Bend Wind Farm
Together with Black & McDonald’s Joint Venture Partner AMEC, the Southern Ontario Utility Region was awarded the Engineering, Procurement and Construction (EPC) contract…

Alectra Electrical Rebuilds
Black & McDonald was trusted with a contract for underground electrical rebuilds for Alectra and Utilities in the Hamilton and St. Catharines area.

EnWin Service Agreement
Black & McDonald was responsible for the Tecumseh Road East feeder extension.

Enbridge Ontario Wind Farm
The AMEC Black & McDonald Joint Venture was contracted to build the following 110 concrete wind turbine foundations and erect 110 wind turbines.

Underwood & Cruickshank Wind Farms
Black & McDonald was contracted to perform a wide range of maintenance services.

MTO – ATMS for various highways
An ATMS needed to be upgraded and reconfigured after the Ministry of Transportation established a new traffic operation centre at 97 Arrow Road…

Enbridge – Talbot Wind Farm
Enbridge’s 99 megawatt Talbot Wind Project generates enough clean energy to power 33,000 homes and offset about 106,600 tonnes of carbon dioxide each…

Clarington Transformer Station
Black & McDonald was engaged to conduct pre-service testing and commissioning of an important transformer station.

Capstone Erie Shores Wind Farm
Black & McDonald’s Field Service Division was contracted to perform a wide range of services, including review design drawings such as single lines,…

Belle River Wind Farm
Black & McDonald was contracted to construct a new 138 kV to 240 kV substation (109 m x 198 m).

K2 Wind Farm
Together with Black & McDonald’s Joint Venture Partner AMEC, Black & McDonald’s Southern Ontario Utility Region was awarded the engineering, procurement and construction…

Minas Energy St. Croix Hydro Dam
Black & McDonald assisted Minas Power with grounding update of its hydro system.

Halifax Airport Taxiway Restoration
Black & McDonald supplied and installed inset lighting, including underground conduit with all associated trenching, backfilling and wiring.

K2 Wind Farm
Black & McDonald’s Southern Ontario Utility Region engineered, procured and constructed the K2 Wind Farm, including installation of 140 Siemens wind turbines.
Get In Touch
Join Our Team
You believe that if something’s worth doing, it’s worth doing right. That solutions should be made to last. That being part of a team means working not just for oneself but for one another. That’s how we operate too.
